One Crescent — Dubai Water Canal
Scroll

Construction Update

ONE CRESCENT

PALM JUMEIRAH

We are delighted to provide you with an update on the progress of One Crescent, to showcase the milestones achieved and anticipated developments ahead.

Progress Status

Q1
Q2
Q3
Q4

ONE CRESCENT

PROGRESS STATUS

One Crescent facade design at golden hour

Design

Concept Design

Completed

Shoring Design

Completed

Schematic Design

Completed

Piling Design

Completed

Detailed Design

Completed

One Crescent facade detail with sculpted balconies

Procurement

Shoring Contractor

Appointed

Piling Contractor

Appointed

Main Works Contractor

Appointed

MEP Contractor

Appointed

Facade Contractor

Appointed

Fit Out Contractor

Appointed

One Crescent tower overlooking the Dubai Water Canal

Authority

Preliminary Design Approval

Obtained

Design NOC's Approval

Obtained

Site Clearance NOC's

Obtained

Shoring Permit

Obtained

Piling Permit

Obtained

Building Permit

Obtained

One Crescent balconies and colonnade at sunset

Siteworks

Shifting Existing Services from Plot

Completed

Shoring Works

Completed

Piling Works

Completed

Dewatering System Installation

Completed

Excavation Works

Completed

Pile Cap Works

Completed

Foundation Works

Completed

Ground Floor Slab

Completed

Structure upto Roof Floor Slab

Completed

Aluminum Glazing Works

Completed

MEP Works

In Progress

ID Fitout Works

In Progress

Updated Timeline

One Crescent facade nearing completion, sculpted balconies at golden hour

Shoring Works

Completed

Piling and Enabling

Completed

Foundation / Raft Works

Completed

Substructure Works

Completed

Superstructure Works

Completed

External Glass Works

Completed

MEP and Finishes Work

Q3 | 2026

Handover

Q4 | 2026

Thank You

For being part of this exciting journey

Aerial map showing One Crescent on the Dubai Water Canal