Construction Update
ONE CRESCENT
PALM JUMEIRAH
We are delighted to provide you with an update on the progress of One Crescent, to showcase the milestones achieved and anticipated developments ahead.
Progress Status
ONE CRESCENT
PROGRESS STATUS

Design
Concept Design
Completed
Shoring Design
Completed
Schematic Design
Completed
Piling Design
Completed
Detailed Design
Completed

Procurement
Shoring Contractor
Appointed
Piling Contractor
Appointed
Main Works Contractor
Appointed
MEP Contractor
Appointed
Facade Contractor
Appointed
Fit Out Contractor
Appointed

Authority
Preliminary Design Approval
Obtained
Design NOC's Approval
Obtained
Site Clearance NOC's
Obtained
Shoring Permit
Obtained
Piling Permit
Obtained
Building Permit
Obtained

Siteworks
Shifting Existing Services from Plot
Completed
Shoring Works
Completed
Piling Works
Completed
Dewatering System Installation
Completed
Excavation Works
Completed
Pile Cap Works
Completed
Foundation Works
Completed
Ground Floor Slab
Completed
Structure upto Roof Floor Slab
Completed
Aluminum Glazing Works
Completed
MEP Works
In Progress
ID Fitout Works
In Progress
Updated Timeline

Shoring Works
Completed
Piling and Enabling
Completed
Foundation / Raft Works
Completed
Substructure Works
Completed
Superstructure Works
Completed
External Glass Works
Completed
MEP and Finishes Work
Q3 | 2026
Handover
Q4 | 2026
Thank You
For being part of this exciting journey